Linebach Funkhouser had a successful year in 2011 remediating petroleum and mixed chlorinated/petroleum contaminated groundwater plumes at several sites across Kentucky. Through the efforts of 4 project managers, LFI has received, or is soon to receive, "No Further Action" letters from the Kentucky Department for Environmental Protection, Underground Storage Tank Branch and the Superfund Branch on a total of eight sites. Six of the sites were the result of petroleum contamination due to historical operations and one site had a release of a combination of chlorinated solvents and petroleum compounds. At six sites, LFI utilized BOS200® and Trap & Treat® a product sold by Remediation Products, Inc. (RPI), which is a specially-formulated blend of activated carbon, sulfate reduction media, micronutrients, and facultative microbes. The seventh and eighth site involving chlorinated solvents was remediated using FMC, Inc's. Klozur®CR, which is a single, formulated product consisting of high pH - activated Klozure Persulfate and PermeOx® Plus engineered calcium peroxide. The addition of the remedial products was through the use of Geoprobe® borings and high pressure injection as well as open-hole soil mixing. Based on groundwater sampling activities, LFI found that BOS200®rapidly reduced or eliminated the identified BTEX contamination to below MCLs at 5 of the 6 sites, with the 6th site being reduced to below its site-specific screening limits based on sampling approximately 3 to 4 months following injection. Long term monitoring (1 year after injection) at the sites did not indicate contamination rebound. LFI conducted long term monitoring (two years of quarterly sampling)of the Klozur®CR site and it also did not indicate contaminant rebound. Below is a chart showing a summary of the sites, area of impact, and material used to successfully obtain closure.

Summary of Sites and Material Applied

Site Location

Area in square feet

Constituents of Concern

Material Applied

Louisville*

5,525

BTEX/PAH

BOS200®

Louisville

3,000

BTEX

BOS200®

Lebanon

3,155

BTEX

BOS200®

Shelbyville

4,000

BTEX

BOS200®

Campbellsville

2,650

BTEX

BOS200®

La Center

570

BTEX

BOS200®

Elizabethtown

1,225

Chlorinated Solvents/BTEX

Klozur® CR

Louisville

5,000

Chlorinated Solvents

Klozur® CR